Project Change Control: What to Approve When Scope Moves

A decision record for changes that move a commitment, not for every task reshuffle.

Jump to the worksheet
two people drawing on whiteboard
Illustrative photograph · Kaleidico / Unsplash

The short answer

A change request asks whether a proposed difference is worth what it does to the agreed plan. Show what it replaces, who pays for it and what the receiving team will have to accept. Record the decision before changing the baseline. An approved request changes the plan; it doesn’t prove that the resulting work is ready.

Draw the line between delivery detail and a baseline change

Teams should be able to change implementation details within their remit. Escalate changes that alter agreed outcomes, acceptance criteria, budget, milestones, an external commitment or another team’s capacity. Agree tolerances and approval authority when work starts. A two-day shift within a workstream may be a normal planning choice. The same shift is a change request if it consumes the only slot a second team has to test before launch.

  1. Log the requested outcome and the reason. Capture which baseline item would change.
  2. Ask affected owners what changes for their work, what is uncertain and who needs to accept it.
  3. Compare doing nothing, changing now and deferring. Include what has to be dropped or moved.
  4. Record the decision and effective date. Then update the schedule, budget, dependencies and acceptance tests together. Tell the people whose work changed.

Ask the requester to describe the problem before naming the feature. “Add three approval routes” is a solution. “Weekend cases must still reach someone authorised to decide” is an outcome, and it leaves room for a simpler option. Capture the current baseline version or the specific promise you’d change. Without that reference, the delivery team may be discussing a new plan while the sponsor believes they’re approving a small clarification.

Put the assessment with people who know the constraints: the team doing the work, the people running it afterwards, anyone whose milestone moves, and whoever owns the cost. Ask for an impact range and the largest unknown. A day of development may need a new supplier test, weekend cover or rework on instructions already in use. Don’t sum up only the first number somebody provides.

A good option paper says what happens if you keep the plan as it is. Sometimes the cost of doing nothing is a workaround operations has already accepted. Sometimes doing nothing leaves you unable to meet a binding requirement; that’s a choice about response, not a vote on whether the requirement exists. If the reason given for urgency isn’t verified, give the request an owner and a deadline to establish it.

Change record to copy

Field Entry
Request and reason Outcome sought and evidence of need
Baseline affected Version, scope item, date or cost line
Impact Delivery, cost, dependencies, benefits and acceptance
Options Keep, defer or approve; trade-off for each
Decision Approver, date, chosen option and limits
Follow-through Which artefacts change, who updates them and how it will be checked

Fictional example: ten working days before a claims process goes live, operations asks for three additional approval routes. The current baseline includes one standard route, and user testing has four days booked. The delivery lead estimates two days to configure and test one route, five for all three, with specialist availability as the main uncertainty. The service owner demonstrates that weekend cases need an alternate approver from day one; the two other routes have a documented manual route for the first month.

The change record shows three choices: launch unchanged and restrict weekend intake, add the weekend route by deferring a non-critical reporting improvement, or add all three and move launch to reopen testing. The sponsor authorises the second option within the existing cost cap. They ask the service owner to sign for the temporary arrangements and the test lead to prove both permitted and denied decisions. The two deferred routes get a review date, not a promise to ship.

On the first test the operator can send a case down the new route but can’t recover it if the named approver is absent. The team doesn’t mark the change complete. It logs a failed acceptance case and asks the service owner to agree how it should be handled. If the existing deadline and cost cap no longer cover the fix, the sponsor gets another decision, not an invoice for a choice they didn’t make.

Use the final row of the record to list the documents or systems to update and the people to tell. Check that the new acceptance cases, schedule and dependency commitments all describe the same choice. If the supplier reads a different scope from the test lead, the form may be finished but the change isn’t controlled.

If a change involves moving money between teams, have finance reflect the authorised decision in the forecast. If the price is unchanged but the receiving team has to add weekend cover, name who agreed to absorb it. Cost doesn’t disappear just because it landed on somebody else’s budget.

The UK project delivery standard sets out change control as a planning and control practice. For changes that alter how staff do their jobs, use a separate change impact assessment.

Frequently asked questions

Open a question to read the full answer.

Does every backlog item need a change request?

No. Use ordinary backlog management for choices inside agreed scope and tolerance. A request becomes material when it moves a commitment or passes work or risk to someone who didn’t agree to it. Where delivery teams are unsure, keep a short rule about who can decide what, with examples from the work. Don’t make teams fill out the same form to rename a button and to move a contracted milestone.

What about urgent changes?

Use the emergency route your organisation has authorised. Write down what was done, why waiting wasn’t viable, who authorised it and how you’ll verify the result. Reconcile the schedule, acceptance evidence and records afterwards. Emergency approval should be time-limited where appropriate. If the measure is temporary, give it an expiry or review date so it doesn’t become permanent through inattention.

Can a change request be approved with conditions?

Yes. State the condition in a way someone can verify: a specified cost limit, a signed dependency or acceptance evidence by a date. Say what work can start before it is met, if any, and who checks it. If the condition fails, follow the agreed fallback or return for a decision. “Approved subject to everything working out” isn’t an instruction a delivery lead can act on.

Who approves a change affecting two teams or a supplier?

One person should own the decision under the applicable delegated authority, but the affected owners must confirm what it does to their commitments. Get the authorised commercial role to handle any contract change. A programme approval isn’t necessarily a customer or supplier agreement. Make both records traceable when both are needed; the teams shouldn’t have to guess which one applies.

How do you track a request that was rejected or deferred?

Keep the decision, rationale and any condition that would reopen it. A deferred request needs a review trigger or date; a rejected one shouldn’t keep consuming planning time unless the facts change. Don’t move either into a committed release by changing its label in the backlog. When it comes back, show what’s different and compare it with today’s baseline.

Next step

Discuss programme controls.

Put this into practice

Use the editable worksheet

Take the decision you’re facing, put an owner against it and record what would change your mind. The download is an editable CSV with no signup.

A GOOD STORY IS A STARTING POINT.

Where does it
take you?

An idea, a question, a different perspective.
I’d like to hear it.

Let’s talk ↗
A CONNECTION STARTS HERE

Let’s talk.

An idea taking shape. A challenge worth solving.
Tell me what’s on your mind.

Your details are used to respond to this enquiry.

The Sunday Blueprint

Sorry. This is the bit
where I interrupt you.

You were happily looking around and now I’m asking for your email. Awkward.

In return, every Sunday I’ll send you The Sunday Blueprint: the things I’ve seen, read, used or learned that week that are actually worth knowing.

Market shifts. Useful tools. Smart ideas. Practical resources. No motivational nonsense.

Just a useful Sunday read to make Monday slightly less painful.

Keith De Alwis
KeithA note from me. Every Sunday.

Free every Sunday. Unsubscribe anytime.