The short answer
A weekly project report should tell the sponsor what changed, what it means for the next milestone and what you need them to decide. Put the decision first. If the sponsor has to read the last page to find out they’re holding up testing, the report hasn’t done its job.
One page to copy
| Field | What to write |
|---|---|
| Decision needed | One sentence: choice, accountable person and date |
| Delivery since last week | Outcomes accepted or rejected, with links to evidence |
| Next milestone | Baseline date, current forecast, confidence and what would change it |
| Cost and scope | Approved baseline, forecast difference and material change requests |
| Top exposure | One or two affected outcomes, each with owner and next action |
| Next week | What should be demonstrably true by the next report |
Start with a decision someone can make. “Testing at risk” isn’t one. “By Thursday, decide whether to defer a legacy export or move the first release by four days” is. Explain what happens if that choice isn’t made. If the named person doesn’t hold the authority, change the recipient or get the question onto the right agenda. Sending the report isn’t a substitute for escalating a decision you need today.
Delivery is what someone accepted, what they didn’t, and what the evidence says. Show why it matters. “Permission testing: twelve passed” is less useful than “Twelve of twenty agreed cases accepted; four untested cases affect supervisor access, so pilot readiness is unproven.” Link the evidence so the sponsor can check it without turning the report into a test log. Name the person who accepted, declined or has yet to review the result.
Keep the approved baseline, your last forecast and the current forecast visible if the date moves. They answer different questions: what was agreed, what you believed last week, and what you think now. If the sponsor approves a rebaseline, record the approval date and the scope that came with it. Don’t quietly rewrite last week’s forecast to make the trend disappear. Costs work much the same way. Show the approved amount, forecast at completion and any relevant unapproved changes separately. Where a cost is still an estimate, say what would change it.
If you use red, amber and green, write definitions before anyone chooses a colour. For example, a team might use amber when a milestone remains achievable but depends on a named action by a date, and red when it cannot be met under the current plan. Those are example definitions, not universal rules. Put the explanation beside the colour. When everything is reported amber because red feels like an admission of failure, the sponsor simply gets the bad news later.
Write “next week” as a result you can check. Instead of “continue investigation”, put “test lead reruns four failing permission cases; service owner accepts or rejects the results on Friday.” Next week’s report can then show what happened without guessing what the previous author meant.
A worked example
Fictional scenario: a team is preparing a customer portal. The approved first release is 4 December and includes a legacy export. Four permissions cases haven’t been accepted. The testing lead needs two days that were meant for export checks, and the same people can’t do both. Here is how that looks using the template:
| Field | Example |
|---|---|
| Decision needed | Sponsor by Thursday noon: defer legacy export to the second release or keep scope and move the first release |
| Delivery since last week | Sixteen of twenty priority scenarios accepted, up from twelve; four permissions cases require retest |
| Next milestone | 4 December approved and previously forecast; 8 December now forecast if all scope stays; 4 December remains possible if export is deferred and retests pass |
| Cost and scope | Keeping scope needs two additional testing days; finance has not yet estimated the cost; no change to the baseline approved |
| Top exposure | Customers without the right role might see restricted records; testing lead owns retest, service owner must accept results |
| Next week | Four permission cases accepted or documented as failed; approved date and scope reflected in the release plan |
The sponsor agrees to defer the export, but a retest still fails. The report the following week shows the scope decision and the failed case separately. It doesn’t report that the sponsor approved the release. The service owner won’t accept the portal with the access failure, so the team revises the forecast and brings back a decision about pilot scope. That’s the distinction to preserve: approving an option is not the same as accepting its result.
Keep your detailed RAID log linked rather than reproduced. Use it to trace the risks, assumptions, issues and dependencies behind the report. The UK project delivery standard sets out planning, control and governance practices; this example is an operating format, not a government reporting requirement.
Frequently asked questions
Open a question to read the full answer.
What if there is no decision this week?
Say “no decision needed” and show which result will produce the next one. For example, the sponsor needn’t do anything until Friday’s trial shows whether staff can process an exception unaided. Then name who will return with options and when. A report can be useful as a record without inventing an ask. If a decision is overdue, don’t bury it under “no new decisions”.
Should the supplier and sponsor get the same report?
Start from the same accepted results, milestones and forecast. Show each audience the details they need and are authorised to see. A supplier may need the failed acceptance scenario and the date to retest, but not your internal commercial fallback or unrelated personnel concerns. Where both sides have actions, share the agreed action and evidence in the place where they’re expected to work from it.
How do you report a date without giving false confidence?
Name the condition that still has to come true and when you’ll be able to prove it. A date that depends on a confirmed hardware delivery is different from a date based on a supplier saying delivery looks possible. Use a range or a conditional date if the uncertainty matters to the sponsor’s choice. Avoid assigning a percentage confidence you can’t explain.
What goes in the report versus the RAID log?
Put exposures that affect the decision or the next milestone on the main page. Link to the log for background, full descriptions and the action history. If an issue appears for the fourth week with no changed action or owner, don’t merely repeat it. Ask what decision would unblock it or record what has to move because it won’t be resolved.
Who signs off a weekly status report?
The delivery lead should verify that the evidence, forecast and figures are represented accurately; an owner with delegated authority makes any decision requested in it. An email saying “thanks” doesn’t authorise a new budget or release date. Record material decisions in the decision log, show them in the next report and make sure the changed plan reaches the people doing the work.