The short answer
If new work changes the price, delivery date or result you’re buying, write down the difference and agree it before the team starts. A short change order should tell the client exactly what the new money buys, what moves on the schedule and how the result will be accepted. Linking to a ticket that says “add another integration” isn’t enough.
A change order works best when it is a small comparison to what you already agreed, not a rewrite of the entire engagement.
Start with the existing scope
Put the original deliverable beside the new request. If the work is needed to meet an existing acceptance criterion, first decide whether it’s a correction within scope rather than an extra. Some changes are genuinely unclear. Write down the scope question and the relevant wording instead of charging against an assumption.
Look for the work behind the visible request. “Add the returns inbox” could mean a second mailbox permission, different attachments, new test cases and a review route. Clarify whether the request is to classify messages, draft replies or send them. Those are different deliverables.
An Azure Boards backlog can record delivery work and its acceptance criteria. Keep the commercial decision separate from such a work item, then link them. The backlog explains what to implement; the change order records what the client agreed to buy.
Copy this change-order worksheet
This is a fictional fixed-price example. It shows the structure, not a suggested rate or schedule.
| Field | Worked example |
|---|---|
| Reference and request | CO-04, linked to the agreed scope and original milestone. Client asks to add the returns inbox to a draft-assist pilot. |
| Before and after | Before: one support inbox. After: the original inbox plus one named returns inbox, with drafts routed to the existing manual review queue. |
| Deliverables | Connect the mailbox, map four returns categories, add a repeat-delivery check and update the operator note. |
| Explicitly excluded | OCR of attachments, historical backfill, extra inboxes and automatic customer replies. |
| Price and recurring delta | Original build £9,000; add £1,800 fixed; revised build £10,800. Incremental usage estimated separately at £25–£60/month under the stated volume assumption, not a fixed amount. |
| Schedule and dependencies | Move the pilot review from 12 to 16 February in this example, subject to named test-mailbox access and sample fixtures by 8 February. If access slips, review the date before authorising additional work. |
| Acceptance | A reviewer checks 24 approved synthetic messages, including duplicates and missing order numbers. Requests with missing order numbers go to manual review, repeated delivery creates one work item, and nothing is sent to customers. |
| Decision and authority | Client budget owner and supplier delivery owner record an approve, decline or defer decision, date and pricing basis. Start only after approval and agreed prerequisites. |
Include the final acceptance owner as well as the budget approver. They may be different people. Microsoft’s user acceptance testing guidance shows how named testers can run assigned tests and report outcomes. You don’t need its tooling to apply that principle.
Set the boundary for a surprise inside a change
In the fictional returns-inbox example, the team discovers that many requests are scans rather than text emails. OCR was excluded. The build team has three sensible options: route those scans to a person, remove that type from the pilot or price OCR as a new decision. It can’t quietly add OCR and send an invoice later. Nor should it quietly drop the scans and report that the pilot handles the whole inbox.
Make the decision visible in the acceptance fixture. Include a scan, mark the expected outcome as manual review and name the person who checks that the review item appears. If that test fails, it is a correction to the approved change. If the client changes the expected outcome to extracting text automatically, that is a new request.
Use versioned decisions when terms change. Keep the original £1,800 proposal, note what was accepted, and link any later price or timeline adjustment to the new evidence. The implementation ticket can move through the usual workflow; it should not be the only place that says who agreed a higher spend or changed the acceptance rule.
Give the client a real choice
Show the effect of saying no or later. Could the original pilot proceed on the planned date with one inbox? Could a small paid discovery cap resolve the mailbox uncertainty, without committing the build? If the request replaces existing work, show the credit or removal as clearly as the new charge.
For a price comparison, give the approver a single before-and-after view. An extra £1,800 and two extra support days are different decisions if the launch is tied to staff training. Record which date moves, what still runs on the original date and which dependency would reopen the decision. For monthly spend, show the expected range and volume behind it, not just the number on the build quote.
For time-and-materials work, agree the rate, estimate and any cap or review point. If new evidence changes the estimate, pause at the agreed point and record the new decision. A change order is most useful before anyone has to explain why an invoice was larger than expected.
Frequently asked questions
Open a question to read the full answer.
Do small requests always need a formal change order?
Use the lightest approval process your engagement allows. A short recorded decision may be enough for a bounded change. Check whether it affects price, schedule, acceptance or ongoing support first. If none of those moves, keep it in the delivery backlog. If several small requests together move the release or create real work, show their combined effect rather than presenting each one as too small to count.
How do we distinguish a defect from an extra?
Start with the current approved scope and acceptance tests. If the workflow was meant to create one work item per source record but now creates duplicates, investigate it as a correction. If the client wants it to ingest a second inbox, show what is new and how you would test it. When the existing wording is ambiguous, settle the interpretation before treating either position as an agreed price.
What if the cost can’t be estimated yet?
Don’t guess the fixed price. Agree a capped investigation with a named deliverable and a stop date. For instance, spend one day checking whether scans contain machine-readable text and estimate the range of review effort. After that, show which options are feasible and what each would cost. Approval of the investigation is not approval of the implementation or of recurring vendor charges.
Who signs off a change, and who accepts the result?
Name the person who can agree the spend and the person who can judge whether the workflow does the right thing. For a returns pilot that might be a budget owner and a support lead. The supplier should name who owns the revised delivery plan. Record each decision in one place, so a request from a project channel isn’t mistaken for authority to change the price.
Should recurring model costs go into a change order?
Yes, when the requested work changes them. Show expected monthly usage separately from the one-off build cost and state what drives the estimate, such as the number of records reviewed or the model used. Name who pays the provider and what happens if usage exceeds the estimate. Where the volume is untested, put a review point in the plan rather than describing an estimate as a cap.
Can we authorise a workaround before pricing the permanent fix?
Yes, if you can state what the workaround will achieve, who will run it and when permission ends. For example, let staff manually tag scans for five days while the supplier measures volume and prices OCR. Record the cost or effort cap and what would trigger a stop. Keep that decision separate from the permanent implementation, especially when the workaround changes how records are handled.
Next step
For scoping an engagement before work begins, see the AI consultancy brief template. For help separating an existing commitment from a proposed extra, see AI consultancy in Dubai or UK AI consultancy.